Construction starts on $917 million Concourse E at O'Hare, adding 24 gates by 2034



What to know
- The $640 million first phase is set to add 14 gates and about 315,000 square feet of passenger space by 2030.
- A $277 million second phase would add 10 more gates after the O'Hare Global Terminal is finished in late 2033.
- Passengers will mainly reach the concourse through an underground tunnel from the new Concourse D, due in late 2028.
Why it matters: The city says the overall ORDNext program will increase O'Hare's gate capacity by about 14%, making room for new routes and destinations.
Drafted with AI from the official source · Approved by Kayhan Kırmızıgül
Source: Mayor's Press Office, November 17, 2026.“Mayor Brandon Johnson Breaks Ground on $917 Million New Concourse E at O’Hare.” Read the original
From the releaseMayor Brandon Johnson Breaks Ground on $917 Million New Concourse E at O’Hare
Spotted an error? Tell us and we will correct it in public. See all corrections.